National Grid Schedule of Road Works
Date Road Area Of Work Closure / Diversion Other Works Map Ref Completed
January till end February 2012 Guildhall Street Phase 1 - Churchgate Street to Abbeygate Street. Ends mid October. Phase 2 - Churchgate Street to Westgate Street. Phase 1 Diversion. Guildhall Street (south) into Westgate Street/Parkway/Robert Boby/Woolhall. Phase 2 Diversion. Whiting Street. Angel Hill j No
February 20th 2012 to 30th March 2012 Crown Street Westgate Street to Honey Hill Area of work will be closed. Diversion via Westgate, College and/or Guildhall and Churchgate Streets. Parkway, Tayfen & Northgate Street. Weight restrictions lifted on C765 Angel Hill and Crown Street. Cornhill n No
Beginning January 2012 to Beginning March Cornhill & Woolhall Street Cornhill & Woolhall Street Woolhall Street closed for first 3 wks. Diversion TBC. Access open to businesses & Market Traders. Crown Street o1 No
Beginning January 2012 to Beginning March Central Walk Central Walk Access will be maintained for pedestrians & businesses In conjunction with Cornhill & Woolhall Street o2 No
Beginning to Mid February 2012* * * *End February – one week. Honey Hill & Sparhawk Street * * * *St Mary’s Square Honey Hill, Sparhawk Street & St Mary’s Square Sparhawk Street closed for duration of works to minimise and reduce through traffic. Cornhill, Central Walk, Honey Hill, Sparhawk Street & St Mary’s Square p No
End February 2012 to Beginning March Eastgate Street The Vinefields None. Residential area. St Mary’s Square q No
Beginning to Mid March 2012 Cotton Lane Cotton Lane Two-way lights in Northgate Street at junction with Cotton Lane. St Mary’s SquareCentral Walk r No